View Application SD21A/0203

View Application SD21A/0203

Date Received:
20/07/2021
Last Action:
13/10/2021, Additional Information
Application Type:
Permission
Submission Type:
Additional Information
Closing Date for Submissions:
Closed
Applicant:
Microsoft Operations Ireland Ltd.
Location:
Grange Castle Business Park, Nangor Road, Clondalkin, Dublin 22
Proposed Development:
Modifications and minor additions to previously approved scheme (Planning Register Reference SD20A/0283) at this site of c.16.23ha (in total) comprising of the following changes to previously approved scheme SD20A/0283; Approved Central Administration Building (CAB), relocation of building to the east by approx. 7m; reconfiguration and setting out of building plans at all levels (including roof level) resulting in increase in building footprint of approximately 170sq.m (from 1,424sq.m to 1,594sq.m) associated changes to building elevations (design and finishes); approved single storey Cafeteria Element, additional basement level below cafeteria to accommodate plant; 9 rooflights (2.8 m diameter) and 9 rooflight (1.8m diameter), inclusion of MEP Plant on roof level including new flue extending approx. 1m above parapet; approved four-storey Office element, parapet at roof level to be raised by approx. 1.1m (increased from approved 19.5m in height to proposed 20.6m); overall increase in GIFA of 395sq.m; reconfiguration of area available for PV panels and sedum roof finish in order to accommodate required MEP equipment at roof levels. approved Data Centres - DUB14 and DUB15, reconfiguration and setting out affecting building locations and plans at all levels (including roof level) resulting in reduction in overall building footprint (for each building) by 48sq.m (from 13,442sq.m to 13,394sq.m), associated changes to staircases design, building elevations design and finishes, increase in parapet height of Vent Houses (at roof level) by approx. 350mm and omission of previously proposed zone of sedum roof finish; overall decrease in GIFA of 1,352sq.m in respect of DUB 14 and decrease of 1,453sq.m in respect of DUB 15; all plant equipment at ground level - reduced in height compared to approved layout so that the screening is deemed not required; DUB 14, reduction in height of approved flues by approx. 650mm, reduction in number of flues from 11 approved to 8 proposed; DUB 15, change to level of ground floor and associated increase in overall building height of approx. 700mm (parapet height increased from approved +83.0m O.D. to proposed +83.7m O.D.); reconfiguration of associated external plant at ground level (including generators / E-Houses & transformers) flues, omission of approved Modular Electrical Rooms (MERs) and associated screening serving approved Data Centres DUB14 &15; relocation, modifications to design and expansion of approved Water Treatment Building and associated plant to include, Water Treatment Tanks, 2 sprinkler tanks and relocated approved pump house (contained in the main Water Treatment Plant building) and 1 generator with additional proposed flue stack (height 30.75m) and 1 transformer; Gas Generator Compound - Relocation & reconfiguration of previously approved gas generator compound including, additional 4 generators (from 20 approved to 24 proposed), omission of approved E-houses; additional 7 electrical rooms, additional 7 flues (from 5 approved to 12 proposed); modifications to approved layout of internal site roads, yards and footpaths; relocation and modifications to design of approved Sprinkler Tanks and Pump Houses, Pump House serving DUB 14, relocated into proposed Water Treatment Building and compound, redesign of approved larger tank into proposed two smaller tanks; Pump House serving DUB 15, relocated to south of DUB15 the north facilitate space for electrical equipment redesign of approved larger tank into proposed two smaller tanks; relocation of Approved Gas Networks Ireland (GNI) gas skid & compound including approved 3 kiosk buildings; modifications to approved car park layouts and landscaping design; modifications to location and design of approved bicycle shelters; modifications to site development works, including underground water and building services provision, landscaping, internal security and compound enclosure fencing, and associated works; the remainder of the development (including permitted temporary construction car parking) to be carried out in accordance with parent permission SD20A/0283. An Environmental Impact Assessment Report (EIAR) has been submitted with this application; The application relates to a development which comprises an activity requiring an integrated pollution prevention and control (IE) licence relating to lands located west of the existing MS Data Centre Campus and also a site located north of the main entrance to the business park from Grange Castle Road.
Decision Due:
10/11/2021

Decision Details

Decision Date:
10/11/2021
Decision:
GRANT PERMISSION
Final Grant Date:
N/A

Documents

Please note: Most documents are in Adobe Acrobat pdf format which is free to download and install. If you have any problems displaying the document in your browser then right-click the link below and save the file to your computer.

Received File Type
07/07/2021 Drawings-General
Site levels Sheet A
Adobe PDF
20/07/2021 Acknowledgement / Validation Letter Adobe PDF
20/07/2021 Acknowledgement / Validation Letter Adobe PDF
20/07/2021 Application - Cover Letter
Document schedule
Adobe PDF
20/07/2021 Application Form - Part A Adobe PDF
20/07/2021 Contiguous Building Elevations
1
Adobe PDF
20/07/2021 Contiguous Building Elevations
2
Adobe PDF
20/07/2021 Contiguous Building Elevations
3
Adobe PDF
20/07/2021 Drainage Network Drawings
Typical Drainage Details
Adobe PDF
20/07/2021 Drainage Network Drawings
Storm & rainwater existing Campus A
Adobe PDF
20/07/2021 Drawings-General
Sprinkler tank & pumphouse
Adobe PDF
20/07/2021 Drawings-General
Water treatment sprinkler pump & tank
Adobe PDF
20/07/2021 Drawings-General
proposed gas compound
Adobe PDF
20/07/2021 Drawings-General
boundary & fence details
Adobe PDF
20/07/2021 Drawings-General
Covered bicycle bay
Adobe PDF
20/07/2021 Drawings-General
tank & pumphouse
Adobe PDF
20/07/2021 Drawings-General
Water Treatment Plant
Adobe PDF
20/07/2021 Drawings-General
Existing site survey
Adobe PDF
20/07/2021 Drawings-General
Site finishes A
Adobe PDF
20/07/2021 Drawings-General
Vehicle tracking Analysis A
Adobe PDF
20/07/2021 Drawings-General
waste drainage A
Adobe PDF
20/07/2021 Drawings-General
Foul & Industrial Waste Drainage
Adobe PDF
20/07/2021 Drawings-General
Surface water drainage A
Adobe PDF
20/07/2021 Drawings-General
Surface water drainage B
Adobe PDF
20/07/2021 Drawings-General
Storm & rainwater updates to ex. Campus B
Adobe PDF
20/07/2021 EIAR
Environmental Impact Statement
Adobe PDF
20/07/2021 EIAR
Volume 111
Adobe PDF
20/07/2021 EIAR
Volume 11 Part 1
Adobe PDF
20/07/2021 EIAR
Volume 11, Part 2
Adobe PDF
20/07/2021 Elevations
External Cladding 90
Adobe PDF
20/07/2021 Elevations
external cladding 91
Adobe PDF
20/07/2021 Elevations
Dub 14
Adobe PDF
20/07/2021 Elevations Adobe PDF
20/07/2021 Elevations
Sheet 1
Adobe PDF
20/07/2021 Elevations
Sheet 2
Adobe PDF
20/07/2021 Elevations
Approved & Proposed
Adobe PDF
20/07/2021 Elevations
Office approved 1
Adobe PDF
20/07/2021 Elevations
proposed 2
Adobe PDF
20/07/2021 Elevations
proposed sheet 3
Adobe PDF
20/07/2021 Floor Plans
prop ground 14
Adobe PDF
20/07/2021 Floor Plans
proposed first
Adobe PDF
20/07/2021 Floor Plans
proposed roof plan
Adobe PDF
20/07/2021 Floor Plans
Proposed ground
Adobe PDF
20/07/2021 Floor Plans
proposed first
Adobe PDF
20/07/2021 Floor Plans
proposed roof
Adobe PDF
20/07/2021 Floor Plans
Office building Sheet 1
Adobe PDF
20/07/2021 Floor Plans
Sheet 3
Adobe PDF
20/07/2021 Floor Plans
proposed basement
Adobe PDF
20/07/2021 Floor Plans
proposed basement
Adobe PDF
20/07/2021 Floor Plans
level 1
Adobe PDF
20/07/2021 Floor Plans
Level 2
Adobe PDF
20/07/2021 Floor Plans
Level 3
Adobe PDF
20/07/2021 Floor Plans
Office level 3
Adobe PDF
20/07/2021 Floor Plans
Proposed Roof
Adobe PDF
20/07/2021 Land owner consent Adobe PDF
20/07/2021 Landscape Plans
& Planting Plan overall
Adobe PDF
20/07/2021 Landscape Plans
Details sheet 1 of 2
Adobe PDF
20/07/2021 Landscape Plans
Planting plan sheet 2 of 2
Adobe PDF
20/07/2021 Landscape Plans
Tree & Hedge Survey 1 of 2
Adobe PDF
20/07/2021 Newspaper Notice Adobe PDF
20/07/2021 Other Assessments
Demolition Waste Management
Adobe PDF
20/07/2021 Other Assessments
Site Waste Management Plan
Adobe PDF
20/07/2021 Other Assessments
Construction Environmental Management Plan
Adobe PDF
20/07/2021 Other Assessments
Architects Design Statement
Adobe PDF
20/07/2021 Other Assessments
Aviation Report
Adobe PDF
20/07/2021 Other Assessments
Engineering Planning Report
Adobe PDF
20/07/2021 Other Assessments
Plume Modelling
Adobe PDF
20/07/2021 Other Assessments
Arbouricultural Site Assessment
Adobe PDF
20/07/2021 Other Assessments
Flood Risk Assessment
Adobe PDF
20/07/2021 Other Assessments
Flood risk assessment drawing
Adobe PDF
20/07/2021 Other Assessments
Site details
Adobe PDF
20/07/2021 Photo Montage Adobe PDF
20/07/2021 Plans, Sections, Elevations
Contractor's carpark approved
Adobe PDF
20/07/2021 Sections
Boundary 1
Adobe PDF
20/07/2021 Sections
2
Adobe PDF
20/07/2021 Sections
3
Adobe PDF
20/07/2021 Sections
1
Adobe PDF
20/07/2021 Sections
2
Adobe PDF
20/07/2021 Sections
Approved & Proposed 3
Adobe PDF
20/07/2021 Sections
4
Adobe PDF
20/07/2021 Sections
Dub 14
Adobe PDF
20/07/2021 Sections
prop Sheet 1
Adobe PDF
20/07/2021 Sections
Approved & proposed
Adobe PDF
20/07/2021 Sections
Office AA,BB,CC proposed
Adobe PDF
20/07/2021 Sections
Proposed office DD,EE
Adobe PDF
20/07/2021 Sections
Section FF,GG
Adobe PDF
20/07/2021 Sections
prop office HH,II
Adobe PDF
20/07/2021 Site Layout
Consent SDCC
Adobe PDF
20/07/2021 Site Layout
Overall
Adobe PDF
20/07/2021 Site Layout Adobe PDF
20/07/2021 Site Layout
Prop Dub15 & Admin building
Adobe PDF
20/07/2021 Site Layout
Site levels Sheet B
Adobe PDF
20/07/2021 Site layout plan
Overall 1
Adobe PDF
20/07/2021 Site layout plan
Overall 2
Adobe PDF
20/07/2021 Site layout plan
Overall proposed 1
Adobe PDF
20/07/2021 Site layout plan
Overall proposed 2
Adobe PDF
20/07/2021 Site layout plan
Proposed DUB 14 & Substation
Adobe PDF
20/07/2021 Site layout plan
Construction phasing drawing
Adobe PDF
20/07/2021 Site layout plan
Site Finishes B
Adobe PDF
20/07/2021 Site layout plan
Vehicle tracking B
Adobe PDF
20/07/2021 Site layout plan
watermain Sheet A
Adobe PDF
20/07/2021 Site layout plan
Lighting layout
Adobe PDF
20/07/2021 Site location map Adobe PDF
20/07/2021 Site location map
Overall
Adobe PDF
20/07/2021 Site location map
Sheet 1
Adobe PDF
20/07/2021 Site location map
Sheet 2
Adobe PDF
20/07/2021 Site Notice Adobe PDF
20/07/2021 Water Supply Plans
Watermain layout A
Adobe PDF
20/07/2021 Water Supply Plans
Watermain layout B
Adobe PDF
20/07/2021 Water Supply Plans
Water Attentunation storage Dub 9 &10
Adobe PDF
20/07/2021 Water Supply Plans
Surface water attenuation Dub 12 & 13
Adobe PDF
20/07/2021 Water Supply Plans
Typical Watermain details
Adobe PDF
21/07/2021 Landscape Plans
Tree & Hedge Survey 2 of 2
Adobe PDF
03/08/2021 Plans, Sections, Elevations
Sheet A
Adobe PDF
10/08/2021 Report Received from External Body
Defence dept.
Adobe PDF
18/08/2021 Report Received from Internal Staff
Water Services
Adobe PDF
20/08/2021 Floor Plans
Sheet 2
Adobe PDF
20/08/2021 Report Received from External Body
Irish Water
Adobe PDF
08/09/2021 Report Received from Internal Staff
Parks
Adobe PDF
13/09/2021 Chief Executives Order
Request Additional Information
Adobe PDF
13/09/2021 Notification of Decision Letters
Request Additional Information
Adobe PDF
13/10/2021 F.I. Receipt Ack. Letter Adobe PDF
13/10/2021 F.I. Received Doc.
cover letter
Adobe PDF
13/10/2021 F.I. Received Doc.
Meadow area & Social space
Adobe PDF
13/10/2021 F.I. Received Doc.
Cover letter
Adobe PDF
13/10/2021 F.I. Received Doc. Adobe PDF
13/10/2021 F.I. Received Doc.
Biodiversity/Green Infracture Strategy
Adobe PDF
13/10/2021 F.I. Received Doc.
Biodiversity Link to woodland
Adobe PDF
13/10/2021 F.I. Received Doc.
Overall masterplan
Adobe PDF
13/10/2021 F.I. Received Doc.
masterplan 1 of 2
Adobe PDF
13/10/2021 F.I. Received Doc.
2 of 2
Adobe PDF
13/10/2021 F.I. Received Doc.
Overall site plan prop
Adobe PDF
13/10/2021 F.I. Received Doc.
Overall proposed 2
Adobe PDF
13/10/2021 F.I. Received Doc.
Enlarged prop DUB 14 & Substation
Adobe PDF
13/10/2021 F.I. Received Doc.
Prop. Dub 15 & Admin building
Adobe PDF
13/10/2021 F.I. Received Doc.
Construction phasing drawing
Adobe PDF
13/10/2021 F.I. Received Doc.
sprinkler system
Adobe PDF
13/10/2021 F.I. Received Doc.
boundary fence & details
Adobe PDF
13/10/2021 F.I. Received Doc.
Site sections 1
Adobe PDF
13/10/2021 F.I. Received Doc.
Site sections 2
Adobe PDF
13/10/2021 F.I. Received Doc.
Surface water Sheet A
Adobe PDF
13/10/2021 F.I. Received Doc.
Surface water sheet B
Adobe PDF
13/10/2021 F.I. Received Doc.
Overall drainage
Adobe PDF
13/10/2021 F.I. Received Doc.
Drainage catchment
Adobe PDF
13/10/2021 F.I. Received Doc.
Drainage details 2
Adobe PDF
13/10/2021 F.I. Received Doc.
document schedule
Adobe PDF
02/11/2021 Report Received from Internal Staff
Water Services A I
Adobe PDF
04/11/2021 Report Received from Internal Staff
Parks A I
Adobe PDF
10/11/2021 Chief Executives Order
GRANT PERMISSION
Adobe PDF
10/11/2021 Notification of Decision Letters
GRANT PERMISSION
Adobe PDF
20/12/2021 Final Grant Adobe PDF
08/02/2022 Submission
All Conditions Cover Letter
Adobe PDF
08/02/2022 Submission
Compliance schedule of documents
Adobe PDF
08/02/2022 Submission
Condition 3
Adobe PDF
08/02/2022 Submission
Condition 3
Adobe PDF
08/02/2022 Submission
Condition 3
Adobe PDF
08/02/2022 Submission
Condition 3
Adobe PDF
08/02/2022 Submission
Condition 3
Adobe PDF
08/02/2022 Submission
Condition 3
Adobe PDF
08/02/2022 Submission
Condition 3
Adobe PDF
08/02/2022 Submission
Condition 3
Adobe PDF
08/02/2022 Submission
Condition 3
Adobe PDF
08/02/2022 Submission
Condition 3
Adobe PDF
08/02/2022 Submission
Condition 3
Adobe PDF
08/02/2022 Submission
Condition 3
Adobe PDF
08/02/2022 Submission
Condition 3
Adobe PDF
08/02/2022 Submission
Condition 3
Adobe PDF
08/02/2022 Submission
Condition 3
Adobe PDF
08/02/2022 Submission
Condition 5; TMP
Adobe PDF
08/02/2022 Submission
Condition 8; CWMP
Adobe PDF
08/02/2022 Submission
Condition 15
Adobe PDF
08/02/2022 Submission
Condition 15
Adobe PDF
08/02/2022 Submission
Condition 15
Adobe PDF
08/02/2022 Submission
Condition 15
Adobe PDF
08/02/2022 Submission
Condition 15
Adobe PDF
08/02/2022 Submission
Condition 12
Adobe PDF
08/02/2022 Submission
Condition 12
Adobe PDF
08/02/2022 Submission
Condition 12
Adobe PDF
08/02/2022 Submission
Condition 12
Adobe PDF
08/02/2022 Submission
Condition 12
Adobe PDF
08/02/2022 Submission
Condition 4 and 9; Responses
Adobe PDF
08/02/2022 Submission
Condition 5 and 8; Developer Letter of Agreement
Adobe PDF
15/02/2022 Submission Acknowledgment
Conditions 3,4,5,8,9,12,15
Adobe PDF
01/04/2022 Notification of Decision Letters
Condition 3 and 9; Compliant
Adobe PDF
04/04/2022 Notification of Decision Letters
Condition 4 and 12; Compliant
Adobe PDF
05/04/2022 Notification of Decision Letters
Condition 15; Compliant
Adobe PDF
11/04/2022 Notification of Decision Letters
Condition 5 and 8; Compliant
Adobe PDF
11/04/2022 Notification of Decision Letters
Condition 5 and 8; Compliant
Adobe PDF