Planning Banner Image

View Application SD22A/0299

View Application SD22A/0299

Date Received:
04/07/2022
Last Action:
04/07/2022
Application Type:
Permission
Submission Type:
New Application
Closing Date for Submissions:
Closed
Applicant:
Citywest Drive Limited Partnership
Location:
Citywest Shopping Centre, Fortunestown, Dublin 24
Proposed Development:
The development will consist of amendments to the Strategic Housing Development permitted under An Bord Pleanála Reference TA065.305556. The proposed amendments comprise the provision of photovoltaic panels on the roofs of all 6 no. blocks, the provision of roof plant at Blocks A, B, C and D, the provision of an ESB substation at Block O that requires the relocation of no. 1 carparking space, and the reconfiguration of the ground floor of Block E to provide an enlarged plant room. These amendments are necessary to service the permitted blocks, improve the energy efficiency of the development, and to meet the requirements of ESB to serve the site. At Block A it is proposed to provide the following: 21 no. photovoltaic panels arranged in 3 no. rows; and a screen plant area accommodating an internal plant room of 13.24 sqm and an external plant area of 34.72 sqm surrounded. The proposed screened plant rises approx. 1 metre above the permitted lift overruns. At Block B it is proposed to provide the following: 21 no. photovoltaic panels arranged in 3 no. rows on the 5-storey section of the permitted building; a red brick internal plant room of 10.3 sqm on the 4-storey section of the building; and a screened external plant area of 29.2 sqm on the 4-storey section of the building. The proposed roof plant rises approx. 1 metre above the permitted lift over run. At Block C it is proposed to provide the following: 21 no. photovoltaic panels arranged in 3 no. rows on the 6-storey section of the permitted building; a red brick internal plant room of 10.3 sqm on the 5-storey section of the building; and a screened plant area of 32 sqm on the 5-storey section of the building. The proposed roof plant rises approx. 1 metre above the permitted lift over run. At Block D it is proposed to provide the following: 21 no. photovoltaic panels arranged in 3 no. rows; a screened with an internal plant room of 13.5 sqm and an external plant area of 24.33 sqm; a c. 3-metre-high red brick ESB substation with LV switch room to the southwest of the Block D, and the ancillary relocation of 1 no. car parking space. The proposed screened plant rises approx. 2 metre above the permitted parapet level. At Block E it is proposed to provide the following; 18 no. photovoltaic panels arranged in 3 no. rows; and the reconfiguration of the ground floor to replace 1 no permitted retail unit with an enlarged Plant Room (117.15 sqm}, ESB substation (13.6 sqm), a Generator Room (21.82 sqm}, and a Low Voltage (L V} switchroom (13.71 sqm}. These works require the removal of existing windows and doors at the permitted retail unit. At Block F it is proposed to provide 18 no. photovoltaic panels arranged in 2 no. rows. These, and all associated site works including landscaping at a site of 2.9 hectares.
Decision Due:
29/08/2022

Documents

Please note: Most documents are in Adobe Acrobat pdf format which is free to download and install. If you have any problems displaying the document in your browser then right-click the link below and save the file to your computer.

Received File Type
04/07/2022 Acknowledgement / Validation Letter Adobe PDF
04/07/2022 Acknowledgement / Validation Letter Adobe PDF
04/07/2022 Application - Cover Letter Adobe PDF
04/07/2022 Application - Cover Letter
& Document schedule
Adobe PDF
04/07/2022 Application - Cover Letter
Doc schedule
Adobe PDF
04/07/2022 Application Form - Part A Adobe PDF
04/07/2022 Appropriate Assessment Screening Report Adobe PDF
04/07/2022 Drawings-General
Roof Plan Block B
Adobe PDF
04/07/2022 Drawings-General
Roof mechanical domestic water
Adobe PDF
04/07/2022 Elevations
N & E
Adobe PDF
04/07/2022 Elevations
Block B S & W
Adobe PDF
04/07/2022 Elevations
Block C North & East
Adobe PDF
04/07/2022 Elevations
Block D S & W elevs
Adobe PDF
04/07/2022 Elevations
Prop. elevs Block D
Adobe PDF
04/07/2022 Elevations
North & East
Adobe PDF
04/07/2022 Elevations
Prop Block E S & W Elevs
Adobe PDF
04/07/2022 Elevations
Block F North & East
Adobe PDF
04/07/2022 Elevations
Cont West
Adobe PDF
04/07/2022 Elevations
Cont North & South
Adobe PDF
04/07/2022 Elevations
Cont North & South
Adobe PDF
04/07/2022 Floor Plans
Block C 5
Adobe PDF
04/07/2022 Floor Plans
Block C Floor 5
Adobe PDF
04/07/2022 Floor Plans
Roof plan Block C
Adobe PDF
04/07/2022 Floor Plans
Roof plan Block D
Adobe PDF
04/07/2022 Floor Plans
Ground Block E
Adobe PDF
04/07/2022 Floor Plans
Roof plan Block E
Adobe PDF
04/07/2022 Floor Plans
Block F roof
Adobe PDF
04/07/2022 Floor Plans
Block B 4th floor
Adobe PDF
04/07/2022 Floor Plans
ground
Adobe PDF
04/07/2022 Floor Plans
Ground floor water services
Adobe PDF
04/07/2022 Floor Plans
Fourth Floor Water & mechanical services
Adobe PDF
04/07/2022 Floor Plans
Fifth floor layout
Adobe PDF
04/07/2022 Landscape Plans
Block D
Adobe PDF
04/07/2022 Landscape Plans
Block D
Adobe PDF
04/07/2022 Newspaper Notice Adobe PDF
04/07/2022 Other Assessments
Roof, Mechanical & Water Services
Adobe PDF
04/07/2022 Plans, Sections, Elevations
Roof plan Block A
Adobe PDF
04/07/2022 Plans, Sections, Elevations
Views & CGI
Adobe PDF
04/07/2022 Sections
Cont AA & BB
Adobe PDF
04/07/2022 Site Layout
Block A
Adobe PDF
04/07/2022 Site Layout
Block A
Adobe PDF
04/07/2022 Site Layout
Roof layout Domestic water
Adobe PDF
04/07/2022 Site layout plan Adobe PDF
04/07/2022 Site Notice Adobe PDF
05/07/2022 Elevations
Block B N & East
Adobe PDF
26/07/2022 Report Received from External Body
Dept of Defence
Adobe PDF
04/08/2022 Site Layout
Substation / switchroom
Adobe PDF
04/08/2022 Site location map Adobe PDF
15/08/2022 Report Received from Internal Staff
Water Services
Adobe PDF
16/08/2022 Report Received from External Body
Irish Water
Adobe PDF
18/08/2022 Report Received from Internal Staff
Roads
Adobe PDF
29/08/2022 Chief Executives Order
Request Additional Information
Adobe PDF
29/08/2022 Notification of Decision Letters
Request Additional Information
Adobe PDF
30/08/2022 Report Received from Internal Staff
Parks
Adobe PDF
11/10/2022 F.I. Receipt Ack. Letter
S.D.C.C.'s ack. letter
Adobe PDF
11/10/2022 F.I. Received Doc.
Agent's cover letter
Adobe PDF
11/10/2022 F.I. Received Doc.
B.M. Engineer's cover letter
Adobe PDF
11/10/2022 F.I. Received Doc.
BM Surface Water design report
Adobe PDF
11/10/2022 F.I. Received Doc.
Surface Water Drainage plans
Adobe PDF
11/10/2022 F.I. Received Doc.
Surface Water cathcment plan
Adobe PDF
11/10/2022 F.I. Received Doc.
Drawing Schedule
Adobe PDF
11/10/2022 F.I. Received Doc.
Site location map
Adobe PDF
11/10/2022 F.I. Received Doc.
Site Layout plan
Adobe PDF
11/10/2022 F.I. Received Doc.
Permited/Compliant Site layout
Adobe PDF
11/10/2022 F.I. Received Doc.
Contiguous North/South Elevations
Adobe PDF
11/10/2022 F.I. Received Doc.
Contiguous West Elevations
Adobe PDF
11/10/2022 F.I. Received Doc.
Contiguous AA & BB Section plans
Adobe PDF
11/10/2022 F.I. Received Doc.
Block A - Roof plans
Adobe PDF
11/10/2022 F.I. Received Doc.
Block A - South/West Elevations
Adobe PDF
11/10/2022 F.I. Received Doc.
Block A - North/East Elevatoins
Adobe PDF
11/10/2022 F.I. Received Doc.
Block B - 4th Floor plans
Adobe PDF
11/10/2022 F.I. Received Doc.
Block B - Roof Plan
Adobe PDF
11/10/2022 F.I. Received Doc.
Block B - South/West Elevations
Adobe PDF
11/10/2022 F.I. Received Doc.
Block B - North/East Elevations
Adobe PDF
11/10/2022 F.I. Received Doc.
Block C - 5th Floor plans
Adobe PDF
11/10/2022 F.I. Received Doc.
Block C - Roof plans
Adobe PDF
11/10/2022 F.I. Received Doc.
Block C - South/West Elevations
Adobe PDF
11/10/2022 F.I. Received Doc.
Block C - North/East Elevations
Adobe PDF
11/10/2022 F.I. Received Doc.
Block D - Roof plans
Adobe PDF
11/10/2022 F.I. Received Doc.
Block D - South/West Elevations
Adobe PDF
11/10/2022 F.I. Received Doc.
Block D - North/East Elevations
Adobe PDF
11/10/2022 F.I. Received Doc.
Block E - Ground floor plan
Adobe PDF
11/10/2022 F.I. Received Doc.
Block E - Roof plan
Adobe PDF
11/10/2022 F.I. Received Doc.
Block E - South/West Elevations
Adobe PDF
11/10/2022 F.I. Received Doc.
Block E - North/East Elevations
Adobe PDF
11/10/2022 F.I. Received Doc.
Block F - Roof plans
Adobe PDF
11/10/2022 F.I. Received Doc.
Block F - South/West Elevations
Adobe PDF
11/10/2022 F.I. Received Doc.
Block F - North/East Elevations
Adobe PDF
27/10/2022 Report Received from Internal Staff
Water Services AI
Adobe PDF
03/11/2022 Report Received from External Body
Irish Water AI
Adobe PDF
07/11/2022 Chief Executives Order
Grant Permission
Adobe PDF
07/11/2022 Notification of Decision Letters
Grant Permission
Adobe PDF
15/12/2022 Final Grant Adobe PDF
14/09/2023 Submission
Condition 5(c) & (d)
Adobe PDF
14/09/2023 Submission
Condition 5(c) & (d)
Adobe PDF
14/09/2023 Submission
Condition 5(c) & (d)
Adobe PDF
14/09/2023 Submission
Condition 5(c) & (d)
Adobe PDF
14/09/2023 Submission
Condition 5(c) & (d)
Adobe PDF
14/09/2023 Submission
Condition 5(c)&(d) - Cover Letter
Adobe PDF
22/09/2023 Submission
Condition 4 - NFA by P.A.
Adobe PDF
22/09/2023 Submission
Condition 4 - NFA by P.A.
Adobe PDF
22/09/2023 Submission
Condition 4 - NFA by P.A.
Adobe PDF
26/04/2024 Submission
Condition 5 (c)(d)
Adobe PDF
26/04/2024 Submission
Condition 5 (c)(d)
Adobe PDF
26/04/2024 Submission
Condition 5 (c)(d)
Adobe PDF
26/04/2024 Submission
Condition 5 (c)(d)
Adobe PDF
26/04/2024 Submission
Condition 5 (c)(d)
Adobe PDF
26/04/2024 Submission
Condition 5 (c)(d)
Adobe PDF
30/04/2024 Submission Acknowledgment
Condition 5 (c)(d) resubmission
Adobe PDF
19/06/2024 Notification of Decision
Condition 5(c) & (d)
Adobe PDF