Date Received:
24/02/2021
Last Action:
14/12/2021, Clarification of Additional Information
Application Type:
Permission
Submission Type:
Clarification of Additional Information
Closing Date for Submissions:
Closed
Applicant:
EdgeConneX Ireland Limited
Location:
Site within the townland of Ballymakaily, West of Newcastle Road (R120), Lucan, Co. Dublin
Proposed Development:
Construction of two single storey data centres with associated office and service areas; and three gas powered generation plant buildings with an overall gross floor area of 24,624sq.m that will comprise of the following: Demolition of abandoned single storey dwelling, remaining agricultural shed and derelict former farm building; Construction of 2 single storey data centres (12,797sq.m), both with associated plant at roof level, with 24 standby diesel generators with associated flues (each 25m high) that will be attached to a single storey goods receiving area/store and a single storey office area (2,404sq.m) located to the west of the data centres as well as associated water tower and sprinkler tank and other services; Amendments to the internal access road and omission of access to loading bay permitted under SDCC planning Ref. SD19A/0042/ABP Ref. PL06S.305948 that include the relocation of permitted, and new, internal security gates; and new internal access roads to serve the proposed development that will provide access to 39 new car parking spaces (including 4 electric and 2 disabled spaces) and sheltered bicycle parking to serve the new data centres; The development will also include the phased development of 3 two storey gas powered generation plants (9,286sq.m) within three individual buildings and ancillary development to provide power to facilitate the development of the overall site to be located within the south-west part of the overall site. Gas plant 1 (3,045sq.m) will contain 20 generator units (18+2) with associated flues (each 25m high) will facilitate, once operational the decommissioning of the temporary Gas Powered Generation Plant within its open compound as granted under SDCC Planning Ref. SD19A/0042/ABP Ref. PL06S.305948. Gas plant 2 (3,045sq.m) will contain 20 generator units (18+2) with associated flues (each 25m high). and, Gas plant 3 (3,196sq.m) will contain 21 generator units (19+2) with associated flues (each 25m high). These plants will be built to provide power to each data centre, if and, when required. The gas plants will be required as back up power generation once the permitted power connection via the permitted substation is achieved; New attenuation pond to the north of the site; Green walls are proposed on the southern elevation of each power plant, as well as to the northern elevation of the generator compound of the data centres, and enclosing the water tower/pump room compound, and a new hedgerow is proposed linking east and west of the site; Proposed above ground gas installation compound to contain single storey kiosk (93sq.m) and boiler room (44sq.m). The development will also include ancillary site works, connections to existing infrastructural services as well as fencing and signage. The development will include minor modifications to the permitted landscaping to the west of the site as granted under SDCC planning Ref. SD19A/0042/ABP Ref. PL06S.305948. The site will remain enclosed by landscaping to all boundaries. The development will be accessed off the R120 via the permitted access granted under SDCC planning Ref. SD19A/0042/ABP Ref. PL06S.305948. An EPA-Industrial Emissions (IE) licence will be applied for to facilitate the operation of the gas powered generation plant. An Environment Impact Assessment Report (EIAR) has been submitted with this application. All on a site of 22.1hectares.
Decision Due:
19/01/2022

Decision Details

Decision Date:
19/01/2022
Decision:
GRANT PERMISSION
Final Grant Date:
N/A

Appeal to An Bord Pleanala

Notified:
18/02/2022
Lodged:
15/02/2022
Appellant Type:
1 st Party
Nature of Appeal:
Condition

Decision of An Bord Pleanala

Decision Date:
09/03/2022
Decision:
Appeal Withdrawn

Documents

Please note: Most documents are in Adobe Acrobat pdf format which is free to download and install. If you have any problems displaying the document in your browser then right-click the link below and save the file to your computer.

Received File Type
24/02/2021 Acknowledgement / Validation Letter Adobe PDF
24/02/2021 Appendices 3 Adobe PDF
24/02/2021 Appendices 3 Adobe PDF
24/02/2021 Appendices 3 Adobe PDF
24/02/2021 Appendices 3 Adobe PDF
24/02/2021 Application - Cover Letter Adobe PDF
24/02/2021 Application Form - Part A Adobe PDF
24/02/2021 Appropriate Assessment Screening Report Adobe PDF
24/02/2021 Drainage Network Drawings
Dub 05 Wastewater Details
Adobe PDF
24/02/2021 Drawings-General
external works gas plant
Adobe PDF
24/02/2021 EIAR
Part 1
Adobe PDF
24/02/2021 EIAR
Part 1
Adobe PDF
24/02/2021 EIAR
Part 1
Adobe PDF
24/02/2021 EIAR
Non Technical Summary
Adobe PDF
24/02/2021 Elevations
contig proposed
Adobe PDF
24/02/2021 Elevations
Proposed North/West
Adobe PDF
24/02/2021 Elevations
prop East/South
Adobe PDF
24/02/2021 Elevations
Site access
Adobe PDF
24/02/2021 Elevations
Power Generation 1
Adobe PDF
24/02/2021 Elevations
Power plant 2
Adobe PDF
24/02/2021 Floor Plans
ground proposed
Adobe PDF
24/02/2021 Landscape Plans
Masterplan
Adobe PDF
24/02/2021 Landscape Plans
Sections
Adobe PDF
24/02/2021 Landscape Plans
Planting plan
Adobe PDF
24/02/2021 Landscape Plans
proposed earthworks
Adobe PDF
24/02/2021 Landscape Plans
Tree Constraints
Adobe PDF
24/02/2021 Landscape Plans
The Tree File
Adobe PDF
24/02/2021 Landscape Plans
& Specification
Adobe PDF
24/02/2021 Newspaper Notice Adobe PDF
24/02/2021 Other Assessments
Heat Recovery Feasibility
Adobe PDF
24/02/2021 Other Assessments
Flood Risk
Adobe PDF
24/02/2021 Other Assessments
Engineering
Adobe PDF
24/02/2021 Other Assessments
Marston Consultants
Adobe PDF
24/02/2021 Other Assessments
Architectural Design Statement
Adobe PDF
24/02/2021 Other Assessments
Site Environmental Plan
Adobe PDF
24/02/2021 Other Assessments
Construction Management Plan
Adobe PDF
24/02/2021 Photo Montage Adobe PDF
24/02/2021 Plans, Sections, Elevations
Power Plant 2
Adobe PDF
24/02/2021 Plans, Sections, Elevations
Power Plant 3 elevations
Adobe PDF
24/02/2021 Plans, Sections, Elevations
Roof Plan
Adobe PDF
24/02/2021 Road Layout Plan
Autotrack layout low loader
Adobe PDF
24/02/2021 Sections
Power generation plant 1
Adobe PDF
24/02/2021 Sections
Powerr Generator 3
Adobe PDF
24/02/2021 Sections
prop
Adobe PDF
24/02/2021 Site Layout
permitted
Adobe PDF
24/02/2021 Site Layout
permitted
Adobe PDF
24/02/2021 Site Layout
proposed
Adobe PDF
24/02/2021 Site Layout
Demolished Buildings
Adobe PDF
24/02/2021 Site Layout
Gas Network
Adobe PDF
24/02/2021 Site Layout
Data centre drainage
Adobe PDF
24/02/2021 Site Layout
Drainage Layout
Adobe PDF
24/02/2021 Site Layout
Gas Plant drainage
Adobe PDF
24/02/2021 Site Layout
General layout EDUDUB05
Adobe PDF
24/02/2021 Site Layout
Gneral Access Layout
Adobe PDF
24/02/2021 Site Layout
Autotrack layout low loader East
Adobe PDF
24/02/2021 Site Layout
Crane Acess Gas Plant East
Adobe PDF
24/02/2021 Site Layout
Autotrack Low Loader GasPlant
Adobe PDF
24/02/2021 Site Layout
Autotrack Fire Tender
Adobe PDF
24/02/2021 Site Layout
Autotrack Layout Oil Tanker
Adobe PDF
24/02/2021 Site Layout
Autotrack Layout Crane
Adobe PDF
24/02/2021 Site layout plan
Autotrack Layout Firetender
Adobe PDF
24/02/2021 Site layout plan
Autotrack HGV
Adobe PDF
24/02/2021 Site layout plan
Autotrack Fire Tender 2
Adobe PDF
24/02/2021 Site location map Adobe PDF
24/02/2021 Site Notice Adobe PDF
24/02/2021 Traffic Impact Reports Adobe PDF
24/02/2021 Traffic Impact Reports
Traffic Management Plan
Adobe PDF
24/02/2021 Water Supply Plans
Dub 05
Adobe PDF
24/02/2021 Water Supply Plans
Gas Plant Area
Adobe PDF
24/02/2021 Water Supply Plans
Gas plant
Adobe PDF
24/02/2021 Water Supply Plans
Dub 05 & gas plant
Adobe PDF
18/03/2021 Report Received from External Body
Dept of Defence
Adobe PDF
18/03/2021 Report Received from External Body
Dept of Defence
Adobe PDF
23/03/2021 Submission
P. Mac Fhlannchadha
Adobe PDF
24/03/2021 Drawings-General
EDCDUB05 & Gas Plant
Adobe PDF
29/03/2021 Report Received from Internal Staff
Water Services
Adobe PDF
30/03/2021 Report Received from External Body
An Taisce
Adobe PDF
30/03/2021 Submission
Thornton O'Connor, Town Planning
Adobe PDF
31/03/2021 Report Received from External Body
Irish Water
Adobe PDF
06/04/2021 Report Received from External Body
Waterways Ireland
Adobe PDF
09/04/2021 Report Received from Internal Staff
Roads
Adobe PDF
19/04/2021 Report Received from Internal Staff
Parks
Adobe PDF
20/04/2021 Chief Executives Order
Request Additional Information
Adobe PDF
20/04/2021 Notification of Decision Letters
Request Additional Information
Adobe PDF
20/04/2021 Report Received from External Body
E.H.O.
Adobe PDF
23/04/2021 Notification to third parties and State bodies
Advised Add. Info. Requested
Adobe PDF
02/09/2021 F.I. Received Doc.
ack
Adobe PDF
02/09/2021 F.I. Received Doc.
Site location map
Adobe PDF
02/09/2021 F.I. Received Doc.
layout plan
Adobe PDF
02/09/2021 F.I. Received Doc.
layout zoning
Adobe PDF
02/09/2021 F.I. Received Doc.
Contig elevations
Adobe PDF
02/09/2021 F.I. Received Doc.
proposed contig elev
Adobe PDF
02/09/2021 F.I. Received Doc.
prop bicycle parking
Adobe PDF
02/09/2021 F.I. Received Doc.
Drainage layout
Adobe PDF
02/09/2021 F.I. Received Doc.
Landscape masterplan
Adobe PDF
02/09/2021 F.I. Received Doc.
Landscape Sections
Adobe PDF
02/09/2021 F.I. Received Doc.
Landscape proposals
Adobe PDF
02/09/2021 F.I. Received Doc.
tree pit details
Adobe PDF
02/09/2021 F.I. Received Doc.
Photos
Adobe PDF
02/09/2021 F.I. Received Doc.
Landscape Redport & outline specification
Adobe PDF
02/09/2021 F.I. Received Doc.
Tree File management plan
Adobe PDF
02/09/2021 F.I. Received Doc.
Arch. Design Statement
Adobe PDF
02/09/2021 F.I. Received Doc. Adobe PDF
02/09/2021 F.I. Received Doc.
Awn Consulting
Adobe PDF
02/09/2021 F.I. Received Doc.
Marston Consultancy
Adobe PDF
02/09/2021 F.I. Received Doc.
Ethos Engineering
Adobe PDF
02/09/2021 F.I. Received Doc. Adobe PDF
22/09/2021 Report Received from Internal Staff
Water Services A I
Adobe PDF
24/09/2021 Report Received from External Body
Irish Water AI
Adobe PDF
28/09/2021 Report Received from Internal Staff
Parks AI
Adobe PDF
29/09/2021 Chief Executives Order
Seek Clarification of Additional Information
Adobe PDF
29/09/2021 Notification of Decision Letters
Seek Clarification of Additional Information
Adobe PDF
15/10/2021 Application - Cover Letter
notification of Change of Agent
Adobe PDF
15/10/2021 Chief Executives Order
F.I. Extension Order
Adobe PDF
15/10/2021 FI period extension request
F.I. Extension Request
Adobe PDF
15/10/2021 Notification of Decision Letters
F.I. Extension Notification
Adobe PDF
14/12/2021 F.I. Clarification Letter
SDCC Ack letter
Adobe PDF
14/12/2021 F.I. Received Doc.
Clar. of A.I. Response to request
Adobe PDF
14/12/2021 F.I. Received Doc.
Arboricultural Report
Adobe PDF
14/12/2021 F.I. Received Doc.
Commercial Energy Statement
Adobe PDF
14/12/2021 F.I. Received Doc.
Response
Adobe PDF
14/12/2021 F.I. Received Doc.
Response from Awnconsulting
Adobe PDF
14/12/2021 F.I. Received Doc.
Access & biodiversity 201
Adobe PDF
14/12/2021 F.I. Received Doc.
Landscape Treatment of Bio Swale & Wetland
Adobe PDF
14/12/2021 F.I. Received Doc.
Drainage Layout
Adobe PDF
14/12/2021 F.I. Received Doc.
Drainage Layout Attenuation Pond & Outfall Plan
Adobe PDF
14/12/2021 F.I. Received Doc.
Tree Impacts Plan
Adobe PDF
14/12/2021 F.I. Received Doc.
Tree Constraints Plan
Adobe PDF
14/12/2021 F.I. Received Doc.
Tree Protection Plan
Adobe PDF
14/12/2021 Notification to third parties and State bodies
Advised of Decision
Adobe PDF
08/01/2022 Report Received from External Body
Irish Water Clar of A I
Adobe PDF
19/01/2022 Chief Executives Order
Grant Permission
Adobe PDF
19/01/2022 Notification of Decision Letters
Grant Permission
Adobe PDF
19/01/2022 Notification to third parties and State bodies
Advised Decision
Adobe PDF
19/01/2022 Report Received from Internal Staff
Revised Clar of A I
Adobe PDF
21/02/2022 Appeal Notification
1st Party appeal
Adobe PDF
21/02/2022 Notification to third parties and State bodies
3rd party notifications
Adobe PDF
07/03/2022 Appeal Correspondence
File Cover Letter
Adobe PDF
09/03/2022 Appeal Decision
Appeal Withdrawn
Adobe PDF
11/03/2022 Appeal Submission
SDCC response to ABP
Adobe PDF
24/03/2022 Final Grant Adobe PDF
28/04/2023 Submission
Condition 7
Adobe PDF
28/04/2023 Submission
Condition 7
Adobe PDF
28/04/2023 Submission
Condition 7
Adobe PDF
28/04/2023 Submission
Condition 12 - Arboriculture NFA
Adobe PDF
28/04/2023 Submission
Condition 12 - Arboriculture NFA
Adobe PDF
28/04/2023 Submission
Condition 16 - NFA
Adobe PDF
28/04/2023 Submission
Condition 16 - NFA
Adobe PDF
28/04/2023 Submission
Condition 16 - NFA
Adobe PDF
28/04/2023 Submission
Condition 16 - NFA
Adobe PDF
28/04/2023 Submission
Condition 10 - NFA
Adobe PDF
28/04/2023 Submission
Condition 10 - NFA
Adobe PDF
28/04/2023 Submission
Condition 11
Adobe PDF
28/04/2023 Submission
Condition 11
Adobe PDF
28/04/2023 Submission
Condition 6 - NFA
Adobe PDF
28/04/2023 Submission
Condition 6 - NFA
Adobe PDF
28/04/2023 Submission
Condition 5
Adobe PDF
28/04/2023 Submission
Condition 5
Adobe PDF
28/04/2023 Submission
Condition 5
Adobe PDF
28/04/2023 Submission
Condition 5
Adobe PDF
28/04/2023 Submission
Condition 8
Adobe PDF
28/04/2023 Submission
Condition 8
Adobe PDF
21/06/2023 Notification of Decision Letters
Condition 5 - Compliant
Adobe PDF
21/06/2023 Notification of Decision Letters
Condition 7 - Partially compliant (Not 7 (ii) (b)
Adobe PDF
21/06/2023 Notification of Decision Letters
Condition 11 - Compliant
Adobe PDF
21/06/2023 Notification of Decision Letters
Condition 8 -Partially compliant (only 8(a)
Adobe PDF
09/08/2023 Submission
Condition 4(a)
Adobe PDF
09/08/2023 Submission
Condition 4(a)
Adobe PDF