Planning Banner Image

View Application SD21A/0272

View Application SD21A/0272

Date Received:
04/10/2021
Last Action:
01/02/2022, Additional Information
Application Type:
Permission
Submission Type:
Additional Information
Closing Date for Submissions:
Closed
Applicant:
Irish Water
Location:
Leixlip Water Treatment Plant Site, Cooldrinagh & Backwestonpark lands, Leixlip, Co. Dublin
Proposed Development:
Demolition of existing workshop and (defunct) Activated Carbon Building adjacent the old/northern Treatment Plant Building; construction of a Sulphuric Acid Storage and Dosing Facility Building (single storey up to approximately 8.7 metres in height) adjacent the new/southern Treatment Plant Building; construction of a Lime Storage & Dosing Facility Building (single storey up to approximately 11 metres in height) adjoining the old/northern Treatment Plant Building, associated external storage silos (2) with external staircase (up to approximately 12.3 metres in height) partially enveloped with a perforated metal architectural screen, and ancillary plant and equipment; reconfiguration and repurposing for use as a De-Alkalisation Plant of existing (disused) High-Lift Pump Hall within the old/northern Treatment Plant Building; construction of a new ancillary Workshop Building (single storey up to approximately 4.5 metres in height) to the rear/south of the 'old/northern Treatment Plant Building; temporary and enabling works to facilitate construction and continued / uninterrupted operation of the Treatment Plant site; associated network of underground pipelines/connections, and redirection of existing where necessary, throughout the site; provision of additional car parking (to the rear/south of the old/northern Treatment Plant Building), modification and extension of existing drainage, utility and services infrastructure and connections to serve and facilitate new and reconfigured buildings, and all other associated and ancillary development and works above and below ground level.
Decision Due:
28/02/2022

Decision Details

Decision Date:
28/02/2022
Decision:
GRANT PERMISSION
Final Grant Date:
N/A

Documents

Please note: Most documents are in Adobe Acrobat pdf format which is free to download and install. If you have any problems displaying the document in your browser then right-click the link below and save the file to your computer.

Received File Type
04/10/2021 Acknowledgement / Validation Letter Adobe PDF
04/10/2021 Application - Cover Letter
x 2
Adobe PDF
04/10/2021 Application Form - Part A Adobe PDF
04/10/2021 Appropriate Assessment Screening Report Adobe PDF
04/10/2021 Archaeology Report
& Built heritage
Adobe PDF
04/10/2021 Contiguous Building Elevations Adobe PDF
04/10/2021 Contiguous Building Elevations
existing
Adobe PDF
04/10/2021 Contiguous Building Elevations
proposed contig site
Adobe PDF
04/10/2021 Drainage Network Drawings
prop & existing water drainage profiles
Adobe PDF
04/10/2021 Drawings-General
proposed demolition works
Adobe PDF
04/10/2021 Drawings-General
prop swept path acid delivery
Adobe PDF
04/10/2021 Drawings-General
Swept path analysis lime
Adobe PDF
04/10/2021 EIAR Adobe PDF
04/10/2021 Elevations
Lime dosing proposed
Adobe PDF
04/10/2021 Elevations
proposed acid dosing
Adobe PDF
04/10/2021 Floor Plans
Acid dosing building proposing
Adobe PDF
04/10/2021 Landscape Plans
& Visual Impact
Adobe PDF
04/10/2021 Newspaper Notice Adobe PDF
04/10/2021 Other Assessments
Planning Report
Adobe PDF
04/10/2021 Other Assessments
Design Report
Adobe PDF
04/10/2021 Other Assessments
Construction Environmental Management Plan
Adobe PDF
04/10/2021 Other Assessments
Invasive Species Survey Summary Report
Adobe PDF
04/10/2021 Photo Montage
Sight Notice photos
Adobe PDF
04/10/2021 Photo Montage Adobe PDF
04/10/2021 Plans, Sections, Elevations
proposed workshop
Adobe PDF
04/10/2021 Sections
proposed lime dosing
Adobe PDF
04/10/2021 Sections
prop acid dosing
Adobe PDF
04/10/2021 Site assessment report
Flood Risk
Adobe PDF
04/10/2021 Site Layout
existing
Adobe PDF
04/10/2021 Site Layout
proposed
Adobe PDF
04/10/2021 Site Layout
Proposed upgrade 1
Adobe PDF
04/10/2021 Site Layout
Proposed Lime dosing
Adobe PDF
04/10/2021 Site Layout
swept path analysis 1
Adobe PDF
04/10/2021 Site layout plan
existing upgrade
Adobe PDF
04/10/2021 Site layout plan
existing upgrade 2
Adobe PDF
04/10/2021 Site layout plan
proposed part 2
Adobe PDF
04/10/2021 Site location map Adobe PDF
04/10/2021 Site location map
2
Adobe PDF
04/10/2021 Site Notice Adobe PDF
04/10/2021 Water Supply Plans
Prop & Ext drainage plan & profile
Adobe PDF
04/10/2021 Water Supply Plans
prop & exist surface drainage
Adobe PDF
04/10/2021 Water Supply Plans
Drainage profile prop & exist
Adobe PDF
04/10/2021 Water Supply Plans
proposed lime delivery route
Adobe PDF
04/10/2021 Water Supply Plans
prop acid delivery route
Adobe PDF
29/11/2021 Chief Executives Order
Request Additional Information
Adobe PDF
29/11/2021 Notification of Decision Letters
Request Additional Information
Adobe PDF
01/02/2022 Drainage Network Drawings
prop & exist surface water
Adobe PDF
01/02/2022 Drainage Network Drawings
Prop & Existing Surface water drainage
Adobe PDF
01/02/2022 Drawings-General
Surface water drainage plans
Adobe PDF
01/02/2022 Drawings-General
Prop & exist surface water drainage 2
Adobe PDF
01/02/2022 Drawings-General
proposed lime delivery route
Adobe PDF
01/02/2022 Drawings-General
proposed acid delivery route
Adobe PDF
01/02/2022 Drawings-General
Swept path analysis 1
Adobe PDF
01/02/2022 Drawings-General
Swept path acid analyisis 2
Adobe PDF
01/02/2022 Drawings-General
Swept path analysis lime
Adobe PDF
01/02/2022 F.I. Received Doc.
Ack
Adobe PDF
01/02/2022 F.I. Received Doc.
doc schedule
Adobe PDF
01/02/2022 F.I. Received Doc. Adobe PDF
01/02/2022 F.I. Received Doc.
Site location
Adobe PDF
01/02/2022 F.I. Received Doc.
Contig elevations
Adobe PDF
01/02/2022 Site Layout
ex
Adobe PDF
01/02/2022 Site Layout
proposed
Adobe PDF
01/02/2022 Site Layout
Ex Part 1
Adobe PDF
01/02/2022 Site Layout
Existing Part 2
Adobe PDF
01/02/2022 Site Layout
proposed part 1
Adobe PDF
01/02/2022 Site Layout
Proposed part 2 upgrade
Adobe PDF
01/02/2022 Site layout plan
Prop demolition
Adobe PDF
01/02/2022 Site location map
prop 2
Adobe PDF
16/02/2022 Report Received from Internal Staff
Water Services A I
Adobe PDF
18/02/2022 Report Received from External Body
Irish Water AI
Adobe PDF
24/02/2022 Report Received from Internal Staff
Parks AI
Adobe PDF
28/02/2022 Chief Executives Order
Grant Permission
Adobe PDF
28/02/2022 Notification of Decision Letters
Grant Permission
Adobe PDF
13/04/2022 Final Grant Adobe PDF
26/07/2022 Submission
Condition 8
Adobe PDF
26/07/2022 Submission
Condition 8
Adobe PDF
26/07/2022 Submission
Condition 8
Adobe PDF
26/07/2022 Submission
Condition 8
Adobe PDF
26/07/2022 Submission
Condition 8
Adobe PDF
26/07/2022 Submission
Condition 8; TMP
Adobe PDF
26/07/2022 Submission
Condition 9; CEMP Not for agree
Adobe PDF
26/07/2022 Submission
Condition 6; Not for agree
Adobe PDF
26/07/2022 Submission
Condition 5; Not for agree
Adobe PDF
26/07/2022 Submission
Condition 5; Not for agree
Adobe PDF
26/07/2022 Submission
Condition 2
Adobe PDF
26/07/2022 Submission
Condition 2, 4, 5, 6 , 8 and 9; Cover Letters
Adobe PDF
26/07/2022 Submission
Condition 2, 4, 5, 6 , 8 and 9; Cover Letters
Adobe PDF
26/07/2022 Submission
Condition 4; Not for agree
Adobe PDF
29/07/2022 Submission Acknowledgment
Condition 2 and 8
Adobe PDF
20/09/2022 Notification of Decision Letters
Compliance with con. 8 partially approved
Word Document
20/09/2022 Notification of Decision Letters
Compliance with condition 2
Adobe PDF
13/10/2022 Submission
Condition 2; Not for agreement
Adobe PDF
13/10/2022 Submission
Condition 2; Not for agreement
Adobe PDF