- Date Received:
- 21/06/2021
- Last Action:
- 09/02/2022, Additional Information
- Application Type:
- Permission
- Submission Type:
- Additional Information
- Closing Date for Submissions:
- Closed
- Applicant:
- ERF Lucan Investment DAC
- Location:
- Lucan Shopping Centre, Newcastle Road, Co. Dublin
- Proposed Development:
- Two-storey commercial building providing two new units and ancillary accommodation (1,574sq.m gross floor area); Unit 1 will be used as a shop (1,057sq.m), Unit 2 will be used for professional services or health centre or office or gymnasium ( 517sq.m); the development will also consist of roof plant and PV panels; Lucan advertising signage (50sq.m) and other indicative illuminated signage zones; extended service yard and new access gates; new pedestrian linkage to adjoining Somerton site; reconfigured customer car park and new vehicle charging infrastructure; standalone substation/switch room (30sq.m); hard and soft landscaping, and pedestrian canopy; connection to services; all associated site and development works.
- Decision Due:
- 08/03/2022
Decision Details
- Decision Date:
- 08/03/2022
- Decision:
- GRANT PERMISSION
- Final Grant Date:
- N/A
Appeal to An Bord Pleanala
- Notified:
- 29/03/2022
- Lodged:
- 25/03/2022
- Appellant Type:
- 3RD PARTY
- Nature of Appeal:
- AGAINST DECISION
Documents
Please note: Most documents are in Adobe Acrobat pdf format which is free to download and install. If you have any problems displaying the document in your browser then right-click the link below and save the file to your computer.
Received | File | Type |
---|---|---|
21/06/2021 | Acknowledgement / Validation Letter | Adobe PDF |
21/06/2021 | Application - Cover Letter | Adobe PDF |
21/06/2021 | Application Form - Part A | Adobe PDF |
21/06/2021 | Appropriate Assessment Screening Report | Adobe PDF |
21/06/2021 |
Drawings-General
Drainage Layout |
Adobe PDF |
21/06/2021 |
Drawings-General
Site Drainage Details |
Adobe PDF |
21/06/2021 |
Drawings-General
Topographical Survey |
Adobe PDF |
21/06/2021 |
Elevations
Proposed |
Adobe PDF |
21/06/2021 |
Elevations
Sheet 1 of 3 |
Adobe PDF |
21/06/2021 |
Elevations
Sheet 2 of 3 |
Adobe PDF |
21/06/2021 |
Elevations
Sheet 3 of 3 |
Adobe PDF |
21/06/2021 |
Floor Plans
Proposed |
Adobe PDF |
21/06/2021 | Newspaper Notice | Adobe PDF |
21/06/2021 |
Other Assessments
Retail Statement |
Adobe PDF |
21/06/2021 |
Other Assessments
Planning Statement |
Adobe PDF |
21/06/2021 |
Other Assessments
Proposed Development - Final Report |
Adobe PDF |
21/06/2021 |
Other Assessments
Proposed Redevelopment |
Adobe PDF |
21/06/2021 |
Other Assessments
Preliminary Energy Assessment Report |
Adobe PDF |
21/06/2021 |
Other Assessments
Planning Submission Engineering Report |
Adobe PDF |
21/06/2021 |
Other Assessments
Preliminary Construction Management Plan |
Adobe PDF |
21/06/2021 |
Other Assessments
Design Statement |
Adobe PDF |
21/06/2021 |
Sections
Proposed |
Adobe PDF |
21/06/2021 |
Site layout plan
and Landscaping Plan |
Adobe PDF |
21/06/2021 | Site location map | Adobe PDF |
21/06/2021 | Site Notice | Adobe PDF |
12/07/2021 |
Submission
J. & C. Hayes |
Adobe PDF |
16/07/2021 |
Submission
J. O'Shea |
Adobe PDF |
21/07/2021 |
Submission
B. & L. Duffy |
Adobe PDF |
22/07/2021 |
Report Received from Internal Staff
Water Services |
Adobe PDF |
22/07/2021 |
Submission
S. & V. Gamble |
Adobe PDF |
26/07/2021 |
Submission
Tesco Ireland Limited |
Adobe PDF |
26/07/2021 |
Submission
Musgrave Operating Partners Ireland |
Adobe PDF |
26/07/2021 |
Submission
C. &. T. Butler Ollry |
Adobe PDF |
27/07/2021 |
Report Received from External Body
Irish WAter |
Adobe PDF |
27/07/2021 |
Report Received from External Body
E.H.O. |
Adobe PDF |
06/08/2021 |
Report Received from Internal Staff
Parks |
Adobe PDF |
11/08/2021 |
Report Received from External Body
T. I. I. |
Adobe PDF |
16/08/2021 |
Chief Executives Order
Request Additional Information |
Adobe PDF |
16/08/2021 |
Notification of Decision Letters
Request Additional Information |
Adobe PDF |
23/08/2021 |
Notification to third parties and State bodies
Advised SDCC Decision |
Adobe PDF |
09/02/2022 |
F.I. Receipt Ack. Letter
Significant AI received |
Adobe PDF |
09/02/2022 |
F.I. Receipt Ack. Letter
Significant AI received |
Adobe PDF |
09/02/2022 |
F.I. Receipt Ack. Letter
Significant AI received |
Adobe PDF |
09/02/2022 |
F.I. Receipt Ack. Letter
Significant AI received |
Adobe PDF |
09/02/2022 |
F.I. Receipt Ack. Letter
Significant AI received |
Adobe PDF |
09/02/2022 |
F.I. Receipt Ack. Letter
Significant AI received |
Adobe PDF |
09/02/2022 |
F.I. Receipt Ack. Letter
Significant AI received |
Adobe PDF |
09/02/2022 |
F.I. Receipt Ack. Letter
SDCC Ack letter |
Adobe PDF |
09/02/2022 |
F.I. Received Doc.
Response for FI request |
Adobe PDF |
09/02/2022 |
F.I. Received Doc.
AIR Traffic & Transport Response Note |
Adobe PDF |
09/02/2022 |
F.I. Received Doc.
Response to FI request from Savills |
Adobe PDF |
09/02/2022 |
F.I. Received Doc.
Response to FI from The McKenna Pearce Practice |
Adobe PDF |
09/02/2022 |
F.I. Received Doc.
Pre-Connection Enquiry from Irish Water |
Adobe PDF |
09/02/2022 |
F.I. Received Doc.
Noise Impact Assessment |
Adobe PDF |
09/02/2022 |
F.I. Received Doc.
External lighting Design |
Adobe PDF |
09/02/2022 |
F.I. Received Doc.
Site Plan, External Lighting Layout |
Adobe PDF |
09/02/2022 |
F.I. Received Doc.
Arboricultural Assessment, & Tree Protection |
Adobe PDF |
09/02/2022 |
F.I. Received Doc.
Arboricultural Assessment (Keyplan) |
Adobe PDF |
09/02/2022 |
F.I. Received Doc.
Arboricultural Assessment (1of3) |
Adobe PDF |
09/02/2022 |
F.I. Received Doc.
Arboricultural Assessment (2of3) |
Adobe PDF |
09/02/2022 |
F.I. Received Doc.
Arboricultural Assessment (3of3) |
Adobe PDF |
09/02/2022 |
F.I. Received Doc.
Arboricultural Impact (Keyplan) |
Adobe PDF |
09/02/2022 |
F.I. Received Doc.
Arboricultural Impact (1of3) |
Adobe PDF |
09/02/2022 |
F.I. Received Doc.
Arboricultural Impact (2of3) |
Adobe PDF |
09/02/2022 |
F.I. Received Doc.
Design Statement - Revision 02 - AI |
Adobe PDF |
09/02/2022 |
F.I. Received Doc.
Revised Final Report |
Adobe PDF |
09/02/2022 |
F.I. Received Doc.
Service Road & Loading Bay Details |
Adobe PDF |
09/02/2022 |
F.I. Received Doc.
Green Roof Details (C01 Extract) |
Adobe PDF |
09/02/2022 |
F.I. Received Doc.
3D Views |
Adobe PDF |
09/02/2022 |
F.I. Received Doc.
Arboricultural Impact (3of3) |
Adobe PDF |
09/02/2022 |
F.I. Received Doc.
Arboricultural Impact (Keyplan) |
Adobe PDF |
09/02/2022 |
F.I. Received Doc.
Tree protection (1of1) |
Adobe PDF |
09/02/2022 |
F.I. Received Doc.
Proposed Sections |
Adobe PDF |
09/02/2022 |
F.I. Received Doc.
Site Location Map |
Adobe PDF |
09/02/2022 |
F.I. Received Doc.
Site Layout & Landscaping Plans |
Adobe PDF |
09/02/2022 |
F.I. Received Doc.
Proposed Floorplans |
Adobe PDF |
09/02/2022 |
F.I. Received Doc.
Proposed elevations |
Adobe PDF |
22/02/2022 |
Report Received from Internal Staff
Water Srvices AI |
Adobe PDF |
23/02/2022 |
Report Received from External Body
Irish Water AI |
Adobe PDF |
28/02/2022 |
Report Received from Internal Staff
Public Lighting Roads AI |
Adobe PDF |
08/03/2022 |
Chief Executives Order
Grant Permission |
Adobe PDF |
08/03/2022 |
Notification of Decision Letters
Grant Permission |
Adobe PDF |
15/03/2022 |
Notification to third parties and State bodies
Advised Decision |
Adobe PDF |
30/03/2022 |
Appeal Notification
3rd party |
Adobe PDF |
31/03/2022 |
Notification to third parties and State bodies
Advised appeal lodged |
Adobe PDF |
12/04/2022 |
Appeal Correspondence
Cover letter to ABP with file |
Adobe PDF |
26/04/2022 |
Appeal Submission
SDCC reply to ABP |
Adobe PDF |
05/05/2022 |
Appeal Correspondence
Submission Returned |
Adobe PDF |
05/05/2022 |
Appeal Correspondence
Submission |
Adobe PDF |
28/07/2022 |
Appeal Correspondence
Ext of decision date |
Adobe PDF |
19/10/2022 |
Appeal Correspondence
A..B.P.'s letter re decision date |
Adobe PDF |
14/12/2023 |
Appeal Decision
GRANT PERMISSION |
Adobe PDF |