Planning Banner Image

View Application SD21A/0305

View Application SD21A/0305

Date Received:
09/11/2021
Last Action:
19/04/2022, Additional Information
Application Type:
Permission
Submission Type:
Additional Information
Closing Date for Submissions:
Closed
Applicant:
Electrical Waste Management Ltd.
Location:
Tay Lane, Greenogue, Rathcoole, Co. Dublin
Proposed Development:
Alterations to existing granted planning, Ref. SD19A/0065, for a proposed Waste Metal Transfer Facility including Waste Electric & Electronic Equipment (WEEE). The subject alterations for which planning permission is sought for are as follows: (1) Reconfiguration of the floor plan areas as follows: (A) Provision of 535sq.m additional floor area due to introduction of areas as follows - (A.1) Extended display area at ground floor of ancillary office, addition of 46sq.m floor area, (A.2) Extended open plan office at first floor of ancillary office, addition of 20sq.m floor area, (A.3) Single storey ancillary storage facility to the front north-east elevation totalling 166sq.m with overall height 7m, (A.4) Mezzanine area to the south eastern side of Light Industrial Unit, totalling 303sq.m. Alterations listed above result in total building area Increase from 4391sq.m to 4926sq.m as shown at the revised table of gross Internal floor areas & uses. (B) Change of use of 64sq.m of light industrial unit floor area to staff facilities due to the introduction of: (B.1) Enclosed stairs from Light Industrial Unit to ancillary office/staff facilities (overall 31sq.m), (B.2) single storey cleaners store and storage at ground floor to the north-eastern comer of light industrial unit (overall 33sq.m). (C) Change of use of 100sq.m of workshop charging area & staff facilities to workshop area & single storey office/staff facilities. (D) Introduction of full height dividing wall at light industrial unit. 2. Elevations alterations as per list above plus additional alterations as follows: (a) Provision of full height cladding (ground floor to roof) to light industrial unit and ancillary Workshop. (b) Introduction of 11m wide x 6m high open to light industrial unit side (north-western) elevation, (c) Rearrangement of all fire exit & level access doors to light industrial unit & ancillary workshop including omission and addition of the same, (d) Introduction of integrated modular louvre system to light industrial unit rear (south­western) & side (north-western) elevation, (e) Introduction of canopies to the ancillary office main entrance and above 11m wide open & dock levellers to light industrial unit side (north-western) elevation. (3) Site plan alterations as follows: (a) Rearrangement of car parking spaces due to provision of office extended display area to the front (north-eastern) elevation, (b) Provision of new finish floor level to office/staff facilities and Workshop and associated site levels adjustments, (c) Provision of a new boundary fence type (paladin fence) throughout the development, (d) Provision of additional weighbridge - overall 2 proposed and rearrangement of brush wash and steam wash between workshop and site's north-western boundary, (e) Provision of building protection bollards to workshop side elevations (south-east and north­west), (f) Associated drainage adjustments due to the inclusion of the alterations above plus reduction of surface water and foul sewer outfall route as per as built access road and services which serve built developments to the east of the site. All other details such as landscaping, lighting, external surface finishes, Environmental Impact Assessment Report (EIAR), Flood Risk Assessment etc. will remain as per the granted application ref. SD19A/0065.
Decision Due:
16/05/2022

Decision Details

Decision Date:
16/05/2022
Decision:
GRANT PERMISSION
Final Grant Date:
N/A

Documents

Please note: Most documents are in Adobe Acrobat pdf format which is free to download and install. If you have any problems displaying the document in your browser then right-click the link below and save the file to your computer.

Received File Type
09/11/2021 Acknowledgement / Validation Letter
SDCC Ack letter
Adobe PDF
09/11/2021 Application - Cover Letter Adobe PDF
09/11/2021 Application Form - Part A Adobe PDF
09/11/2021 Drainage & Watermain Layout Adobe PDF
09/11/2021 Drainage Design Report Adobe PDF
09/11/2021 Elevations Adobe PDF
09/11/2021 Floor Plans
Ground & First Floor
Adobe PDF
09/11/2021 Floor Plans
Ground & First
Adobe PDF
09/11/2021 Newspaper Notice Adobe PDF
09/11/2021 Plans, Sections, Elevations Adobe PDF
09/11/2021 Schedule of Documents Adobe PDF
09/11/2021 Sections Adobe PDF
09/11/2021 Site layout plan
Site Plan with Swept Paths
Adobe PDF
09/11/2021 Site location map Adobe PDF
09/11/2021 Site Notice Adobe PDF
12/01/2022 Chief Executives Order
Request Further Information
Adobe PDF
12/01/2022 F.I. Request Letter
Request Further Information
Adobe PDF
19/04/2022 F.I. Receipt Ack. Letter
SDCC Ack letter
Adobe PDF
19/04/2022 F.I. Received Doc.
Agent's Response
Adobe PDF
19/04/2022 F.I. Received Doc.
Response
Adobe PDF
19/04/2022 F.I. Received Doc.
Drainage Design Report
Adobe PDF
19/04/2022 F.I. Received Doc.
Site Plan
Adobe PDF
19/04/2022 F.I. Received Doc.
Site Plan with Proposed Fence
Adobe PDF
19/04/2022 F.I. Received Doc.
Drainage & Watermain Layout
Adobe PDF
19/04/2022 F.I. Received Doc.
Block A - Ground & First Floor Plan
Adobe PDF
19/04/2022 F.I. Received Doc.
Block A - Ground & First Floor Plan
Adobe PDF
19/04/2022 F.I. Received Doc.
Block B - Plans, Sections & Elevations
Adobe PDF
19/04/2022 F.I. Received Doc.
Block A - Roof Plan
Adobe PDF
28/04/2022 Report Received from Internal Staff
Water Services AI
Adobe PDF
12/05/2022 Report Received from Internal Staff
Parks AI
Adobe PDF
16/05/2022 Chief Executives Order
Grant Permission
Adobe PDF
16/05/2022 Notification of Decision Letters
Grant Permission
Adobe PDF
30/06/2022 Final Grant Adobe PDF