- Date Received:
- 19/05/2021
- Last Action:
- 11/01/2022, Additional Information
- Application Type:
- Permission
- Submission Type:
- Additional Information
- Closing Date for Submissions:
- Closed
- Applicant:
- John Lydon Carpentry Limited
- Location:
- Sites at 4 & 5, Station Grove, Station Road, Clondalkin, Dublin 22
- Proposed Development:
- Construction of 2 two and a half storey, three-bedroom terrace houses and associated site works attached to the existing two and a half storey house at No. 6 Station Grove which was constructed in 2006; the 2 houses will complete this partially finished housing development which was originally granted permission under planning reference SD05A/0125.
- Decision Due:
- 07/02/2022
Decision Details
- Decision Date:
- 07/02/2022
- Decision:
- GRANT PERMISSION
- Final Grant Date:
- N/A
Documents
Please note: Most documents are in Adobe Acrobat pdf format which is free to download and install. If you have any problems displaying the document in your browser then right-click the link below and save the file to your computer.
Received | File | Type |
---|---|---|
19/05/2021 | Acknowledgement / Validation Letter | Adobe PDF |
19/05/2021 | Application - Cover Letter | Adobe PDF |
19/05/2021 | Application Form - Part A | Adobe PDF |
19/05/2021 |
Elevations
East Gable |
Adobe PDF |
19/05/2021 |
Elevations
Rear |
Adobe PDF |
19/05/2021 |
Floor Plans
Ground |
Adobe PDF |
19/05/2021 |
Floor Plans
First Floor |
Adobe PDF |
19/05/2021 |
Floor Plans
Second Floor |
Adobe PDF |
19/05/2021 | Newspaper Notice | Adobe PDF |
19/05/2021 |
Sections
A-A |
Adobe PDF |
19/05/2021 | Site Layout | Adobe PDF |
19/05/2021 | Site location map | Adobe PDF |
19/05/2021 | Site Notice | Adobe PDF |
04/06/2021 |
Correspondence with Planning Authority
Accommodation Schedule |
Adobe PDF |
22/06/2021 |
Report Received from Internal Staff
Water Services |
Adobe PDF |
23/06/2021 |
Report Received from External Body
Irish Water |
Adobe PDF |
28/06/2021 |
Report Received from External Body
An Taisce |
Adobe PDF |
06/07/2021 |
Report Received from Internal Staff
Parks |
Adobe PDF |
13/07/2021 |
Chief Executives Order
Request Additional Information |
Adobe PDF |
13/07/2021 |
Notification of Decision Letters
Request Additional Information |
Adobe PDF |
11/01/2022 |
F.I. Receipt Ack. Letter
SDCC Ack letter |
Adobe PDF |
11/01/2022 |
F.I. Received Doc.
Access Drawing |
Adobe PDF |
11/01/2022 |
F.I. Received Doc.
Areas to be taken in charge |
Adobe PDF |
11/01/2022 |
F.I. Received Doc.
Design Table & Surface Water Layout |
Adobe PDF |
11/01/2022 |
F.I. Received Doc.
Landscape Planning Proposals |
Adobe PDF |
28/01/2022 |
Report Received from External Body
Irish Water A I |
Adobe PDF |
07/02/2022 |
Chief Executives Order
Grant Permission |
Adobe PDF |
07/02/2022 |
Notification of Decision Letters
Grant Permission |
Adobe PDF |
24/03/2022 | Final Grant | Adobe PDF |